Class 66 (66/0, 66/3, 66/4, 66/5, 66/6, 66/7, 66/8, 66/9)
- Type
- Diesel-electric locomotive
- Built
- 1998-2008 (and 2014-15 low-emission batches)
- Power
- 2,462 kW (3,300 hp)
- Top speed
- 75 mph (121 km/h)
Numbers are stations served.
‹ Freight
The 20 classes found at work on British freight in October 2026, largest freight fleet first: each with its drawing where the site has drawn it, in the livery of the operator with most of them where that livery is drawn, and who runs how many.
unverified Some of these figures are still being checked against an official source or a published history. Which ones ↓
| Class | Type and builder | Built | Power | Top speed | Weight | Size | Bogie | In freight service (as at October 2026) | Drawing |
|---|---|---|---|---|---|---|---|---|---|
Class 08 (and 08/9) shunterstatus and doubtsEnglish Electric 6KT diesel, 2 x EE 506 DC traction motors In use as depot and yard shunters. Class 08 count by operator in 2026 is only partly known; weight 49-51 long tons (49.8-51.8 t).
| Diesel-electric shunter locomotive British Railways works at Crewe, Darlington, Derby, Doncaster and Horwich | 1952-1962 | 298 kW (400 hp) | 15 mph (24 km/h) | 50 t | long 29 ft 3 in8.92 m high 12 ft 9 in3.877 m wide 8 ft 6 in2.591 m | wheels 4 ft 6 in1.372 m | GBRfGB Railfreight 5 FLFreightliner 7 | Drawn (indicative) 4 of 6 dimensions found |
Class 09 shunterstatus and doubtsEnglish Electric 6KT diesel GBRf lists 09002 for sale. Wikipedia counts 25 of the 26 Class 09/0s still in service, without saying who has them.
| Diesel-electric shunter locomotive British Railways at Darlington and Horwich | 1959-1962 (09/0); 1992-93 rebuilds as 09/1, 09/2 | 261 kW (350 hp) | 27 mph (43 km/h) | 49 t | long 29 ft 3 in8.92 m high 12 ft 9 in3.874 m wide 8 ft 6 in2.591 m | wheels 4 ft 6 in1.372 m | GBRfGB Railfreight 2 | Drawn (indicative) 4 of 6 dimensions found |
Class 18 battery-hybrid shunter (Clayton CBD90 Hybrid+)status and doubtsJCB DIESELMAX 430 diesel generator plus 524 kWh lead-acid batteries; DC motors GBRf leased four from Beacon (Aug 2024); Tata Steel and Sellafield also use the type.
| Diesel-battery shunter locomotive Clayton Equipment Company, Burton upon Trent | 2021 onwards (first delivered Feb 2022) | 416 kW (558 hp) | 12 mph (19 km/h) | 90 t | – | – | GBRfGB Railfreight 4 | Drawing to come 0 of 6 dimensions found |
Class 20status and doubtsEnglish Electric 8SVT Mk.II diesel; EE 526 DC motors Few in freight/industrial use: HNRC/Swietelsky (Hope Cement Works), Balfour Beatty (Drain Train). Infobox '6 in service' is undated.
| Diesel-electric locomotive English Electric, Vulcan Foundry and Robert Stephenson and Hawthorns | 1957-1962; 1965-1968 | 746 kW (1,000 hp) | 75 mph (121 km/h) | 73 t | long 46 ft 9 in14.256 m high 12 ft 8 in3.851 m wide 8 ft 9 in2.67 m | wheels 3 ft 7 in1.092 m | HNRCHarry Needle Railroad Company BBBalfour Beatty Rail 2 LSLLocomotive Services Limited 4 | Drawn (indicative) 4 of 6 dimensions found |
Class 37status and doubtsEnglish Electric 12CSVT; DC motors (37/4+ Brush alternator) Still working: Colas infrastructure/freight, Europhoenix (hired to ROG), Loram (37418), HNRC; DRS retired its fleet in 2024; Network Rail uses rebuilt 97/3. 80 mph (129 km/h) with CP7 bogies; weight 102-107 t (37/7 ballasted to 122 t).
| Diesel-electric locomotive English Electric, Vulcan Foundry and Robert Stephenson and Hawthorns | 1960-1965 | 1,305 kW (1,750 hp) | 90 mph (145 km/h) | 105 t | long 61 ft 6 in18.75 m high 12 ft 9 in3.89 m wide 8 ft 11 in2.71 m | wheels 3 ft 9 in1.143 m | ColasColas Rail 8 EPREurophoenix Rail 11 HNRCHarry Needle Railroad Company 5 LSLLocomotive Services Limited 5 WCRWest Coast Railways 9 LoramLoram UK 1 | Drawn (indicative) 4 of 6 dimensions found |
Class 56status and doubtsRuston-Paxman 16RK3CT diesel; Brush TM73-62 motors Run down at Colas during 2025 (two stood down Feb 2025); DCRail has 56103 in traffic, 56091 stored and 56301 bought from preservation in Mar 2025. 16 rebuilt as Class 69. 2026 working count unknown.
| Diesel-electric locomotive Electroputere (56001-030), BREL Doncaster (56031-114), BREL Crewe (56115-135) | 1976-1984 | 2,424 kW (3,250 hp) | 80 mph (129 km/h) | 125 t | long 63 ft 6 in19.35 m high 12 ft 9 in3.89 m wide 9 ft 2 in2.79 m | – | ColasColas Rail 10 DCRDCRail 2 | Drawn (indicative) 3 of 6 dimensions found |
Class 59 (59/0, 59/1, 59/2)status and doubtsEMD 16-645E3C two-stroke V16; 6 x EMD D77B motors Heavy Haul Rail 14 (13 active, 59104 stored), GBRf 59003 (for sale). Mendip Rail's Wikipedia page still lists eight as its own, but with 15 built they are counted here under Heavy Haul Rail. 59/2 max 75 mph (121 km/h). GBRf's page gives 121 t.
| Diesel-electric locomotive GM Electro-Motive Division, La Grange (USA) and London, Ontario | 1985-1995 | 2,500 kW (3,300 hp) | 60 mph (97 km/h) | 126 t | long 70 ft 1 in21.349 m high 12 ft 10 in3.912 m wide 8 ft 8 in2.629 m | centres 43 ft 6 in13.259 m wheelbase 13 ft 7 in4.149 m wheels 3 ft 6 in1.067 m | HHRHeavy Haul Rail 14 GBRfGB Railfreight 1 | Drawn (indicative) 6 of 6 dimensions found |
Class 60status and doubtsMirrlees Blackstone 8MB275T; 6 x Brush TM2161A Slowly returning: GBRf 7 in traffic of 10, Europhoenix/DBIH 66 owned with a handful active (60062, 60063, 60074), DCRail 17 (6 working, 11 stored). DB Cargo has sold its fleet. Weight 129 or 131 t; 'wheelbase' on Wikipedia is 50 ft 2 in (15.3 m; not bogie centres).
| Diesel-electric locomotive Brush Traction, Loughborough | 1989-1993 | 2,310 kW (3,100 hp) | 60 mph (97 km/h) | 129 t | long 70 ft 0 in21.34 m high 13 ft 0 in3.95 m wide 8 ft 8 in2.64 m | – | GBRfGB Railfreight 10 DCRDCRail 17 EPREurophoenix Rail 66 | Drawn (indicative) 3 of 6 dimensions found |
Class 66 (66/0, 66/3, 66/4, 66/5, 66/6, 66/7, 66/8, 66/9)status and doubtsEMD 12N-710G3B-T2 two-stroke V12 (139.6 L); 6 x EMD D43TRC motors; 1,850 kW at the rail Backbone of GB freight. 129.6 t is the UIC II/Stage IIIA weight; original spec 127 t (GBRf's page 127 t). Sub-classes: 66/0 250 built (66001-66250; 223 numbers still in use as 66/0); 66/3 16; 66/4 24 (intermodal, 75 mph (121 km/h)); 66/5 81; 66/6 28 (65 mph (105 km/h), regeared); 66/7 99 (GBRf); 66/8 5 (Colas 66846-850); 66/9 7 (66951-957, low-emission, reduced fuel).
| Diesel-electric locomotive GM Electro-Motive Diesel (EMD), London, Ontario and Muncie, Indiana | 1998-2008 (and 2014-15 low-emission batches) | 2,462 kW (3,300 hp) | 75 mph (121 km/h) | 129.6 t | long 70 ft 3 in21.40 m high 12 ft 10 in3.91 m wide 8 ft 8 in2.63 m | – | DBCDB Cargo UK 137 GBRfGB Railfreight 104 FLFreightliner 46 HHRHeavy Haul Rail 58 DRSDirect Rail Services 19 ColasColas Rail 5 | Drawn (indicative) 3 of 6 dimensions found |
Class 67status and doubtsEMD 12N-710G3B-EC; 4 x EMD D43FM motors Wikipedia (read 22 November 2026): 21 in service, 6 stored and 3 scrapped (67003, 67019 and 67030). Transport for Wales owns 67026 and 67028 (bought 2024) and leases others; Royal Train 67005 and 67006. Weight 88-90 t.
| Diesel-electric locomotive Alstom Meinfesa, Valencia (EMD drive components) | 1999-2000 | 2,386 kW (3,200 hp) | 125 mph (201 km/h) | 89 t | long 64 ft 8 in19.71 m high 12 ft 11 in3.93 m wide 8 ft 11 in2.71 m | centres 38 ft 2 in11.63 m wheelbase 9 ft 2 in2.80 m wheels 3 ft 2 in0.965 m | DBCDB Cargo UK ColasColas Rail 2 | Drawn: see its page 6 of 6 dimensions found |
Class 68 (Stadler UKLight)status and doubtsCaterpillar C175-16 diesel; ABB AC/AC; 4 nose-suspended motors 34 built. DRS about 20 for freight and nuclear, 14 with Chiltern Railways (passenger). Fuel tank up to 5,600 L (Stadler) vs 5,000 L.
| Diesel-electric locomotive Vossloh Espana (2013-15), then Stadler Rail Valencia (2016-17) | 2013-2017 | 2,800 kW (3,750 hp) | 100 mph (161 km/h) | 85 t | – | wheels 3 ft 7 in1.10 m | DRSDirect Rail Services 20 | Drawn: see its page 1 of 6 dimensions found |
Class 69 (rebuilt from Class 56)status and doubtsEMD 12N-710G3B-T2 two-stroke V12 (139.6 L); original motors overhauled 69001-69016, all GBRf. Several in heritage and special liveries (see livery list). 128 t from GBRf's page.
| Diesel-electric locomotive Progress Rail, Longport (rebuild of Class 56 bodies and bogies) | 2020-2025 rebuild | 2,390 kW (3,200 hp) | 80 mph (129 km/h) | 128 t | long 63 ft 6 in19.355 m high 13 ft 0 in3.96 m wide 9 ft 2 in2.792 m | centres 34 ft 5 in10.48 m wheelbase 13 ft 5 in4.10 m wheels 3 ft 9 in1.143 m | GBRfGB Railfreight 16 | Drawn (indicative) 6 of 6 dimensions found |
Class 70 (GE PowerHaul PH37ACmi)status and doubtsGE PowerHaul P616 diesel; 6 AC traction motors (Wikipedia: GE 5GEB30 axle-hung) 19 with Heavy Haul Rail (70001-70020 less 70012; 16 active, 3 stored), 17 with Colas (70801-817). 70012, dropped at Newport in 2011, went back to the US and is a test bed and shunter at Erie. 2,250 kW at the wheel rim. Max speed 75 mph (120 km/h; Akiem).
| Diesel-electric locomotive General Electric, Erie, Pennsylvania | 2009-2011 (Akiem: 2009-2012) | 2,750 kW (3,690 hp) | 75 mph (121 km/h) | 129 t | long 71 ft 3 in21.71 m high 12 ft 10 in3.917 m wide 8 ft 8 in2.642 m | wheels 3 ft 6 in1.067 m | HHRHeavy Haul Rail 19 ColasColas Rail 17 | Drawn (indicative) 4 of 6 dimensions found |
Class 73 (73/1 and 73/9)status and doubts750 V DC third rail (1,600 hp one-hour); 73/1: EE 4SRKT diesel 600 hp; 73/9: Cummins QSK19 or MTU 8V 4000 R43L GBRf: 9 x 73/1 and 11 x 73/9 (5 'Tier 1' for Network Rail, 6 'Tier 2' for Caledonian Sleeper, passenger). Network Rail sold its two 73/9 in 2023. Weight 76.8 long tons (78.0 t) Wikipedia; 77 t GBRf page.
| Electro-diesel (third rail and diesel) locomotive English Electric, Vulcan Foundry (73/9: rebuilt by Brush Traction/Wabtec from 2013) | 1965-1967; 73/9 rebuilds 2013 onward | 1,193 kW (1,600 hp) | 90 mph (145 km/h) | 77 t | long 53 ft 8 in16.36 m | wheels 3 ft 4 in1.016 m | GBRfGB Railfreight 20 HNRCHarry Needle Railroad Company 2 | Drawing to come 2 of 6 dimensions found |
Class 88 (Stadler UKDUAL)status and doubts25 kV AC pantograph; Caterpillar C27 Stage IIB diesel (708 kW); ABB AC/AC 88001-88010, all with DRS, owned by Beacon. Diesel power 708 kW (Stadler; Wikipedia 700 kW). 21.5 t axle load.
| Electro-diesel locomotive Vossloh Espana / Stadler Rail Valencia | 2015-2016 | 4,000 kW (5,360 hp) | 100 mph (161 km/h) | 86 t | – | wheels 3 ft 6 in1.067 m | DRSDirect Rail Services 10 | Drawn (indicative) 1 of 6 dimensions found |
Class 90status and doubts25 kV AC; 4 x GEC 412 motors Freightliner (CMA CGM) 27 plus 90050 on loan to Crewe Heritage Centre; LSL 3 for charters; DB Cargo's fleet is stored or scrapped. The in-service total is the Freightliner freight fleet (27); 50 were built.
| Electric locomotive BREL Crewe Works | 1987-1990 | 3,730 kW (5,000 hp) | 110 mph (177 km/h) | 84.5 t | long 61 ft 6 in18.75 m high 13 ft 0 in3.969 m wide 8 ft 10 in2.70 m | centres 32 ft 9 in9.98 m wheelbase 10 ft 9 in3.28 m wheels 3 ft 10 in1.156 m | FLFreightliner 27 LSLLocomotive Services Limited 3 DBCDB Cargo UK 0 | Drawn (indicative) 6 of 6 dimensions found |
Class 92status and doubts6 x Brush asynchronous AC motors; 25 kV overhead or 750 V third rail GBRf 12 (Caledonian Sleeper and Channel Tunnel freight); DB Cargo 4 active of a stored fleet; 13 exported, to Bulgaria, Romania and Croatia. GBRf's page says 90 mph (145 km/h) and 126 t. RAIL (Oct 2026): increasingly unreliable.
| Electric (25 kV AC and 750 V DC) locomotive ABB Transportation and Brush Traction | 1993-1996 | 5,040 kW (6,760 hp) | 87 mph (140 km/h) | 126 t | long 70 ft 1 in21.36 m high 13 ft 0 in3.96 m wide 8 ft 8 in2.64 m | centres 41 ft 11 in12.764 m wheelbase 14 ft 1 in4.29 m wheels 3 ft 9 in1.14 m | GBRfGB Railfreight 12 DBCDB Cargo UK 4 | Drawn: see its page 6 of 6 dimensions found |
Class 93 (Stadler tri-mode)status and doubts25 kV AC (4,000 kW, boost 4,600), CAT C32 Stage V diesel (900 kW), two LTO batteries (400 kW) Ten delivered to ROG; entered service Oct 2025; trial runs for DB Cargo (10 Feb 2026) and Freightliner; stored at DRS Gresty Bridge; no regular freight contract yet. Width 8 ft 10 in (2,690 mm) is the carbody width.
| Electro-diesel-battery locomotive Stadler Rail Valencia | 2022-2024 (10 built) | 4,000 kW (5,360 hp) | 110 mph (177 km/h) | 86 t | long 69 ft 7 in21.22 m wide 8 ft 10 in2.69 m | – | ROGRail Operations Group 10 | Drawn (indicative) 2 of 6 dimensions found |
Class 97/3 (Network Rail ERTMS rebuilds of Class 37)status and doubts97301 (stored), 97302, 97303 'Dave Berry', 97304 'John Tiley'; autumn rail-head treatment and ERTMS tests on the Cambrian lines.
| Diesel-electric locomotive English Electric (original Class 37); rebuilt by Network Rail at Barrow Hill | built 1960-65; rebuilt 2008 | as Class 37 plus ERTMS equipment | – | – | – | – | NRNetwork Rail 4 | Drawn (indicative) 0 of 6 dimensions found |
Class 99 (Stadler)status and doubts25 kV AC (6,170 kW at wheel rim) plus Cummins QSK50 Stage V diesel (1,790 kW); AC/AC; HVO fuel; tractive effort 500 kN 99001 first commercial train 28 July 2026; at least 99001-99013 delivered by Sept 2026 (99013 appears in a RAIL report). 99001-020 no train supply, 99021-030 with ETS (for Belmond). 13 more may be ordered for Caledonian Sleeper (not confirmed).
| Electro-diesel (bi-mode) locomotive Stadler Rail Valencia (for Beacon Rail) | 2025 onward (30 ordered; first two arrived 10 June 2025) | 6,170 kW (8,270 hp) | 75 mph (121 km/h) | 113 t | – | – | GBRfGB Railfreight 13 | Drawing to come 0 of 6 dimensions found |
Left out: Classes 47, 57 and 86, because no freight work was found for them in 2026. The Class 93 is stored, with no freight contract yet. Counts come from sources of different dates and are indicative.
How we source figures → · Spotted a mistake? Tell us → (opens in a new tab)
Know a source for one of these? Send it to us → (opens in a new tab)